Important Reminder: Article 103 of the new ACR (600-2024) concerning the 15% Advance Payment

Important Reminder

Compared to the previous regulations, Article 103 of the new ACR (pursuant to Decision No. 600-2024) introduces a fundamental change in the method of releasing the advance payment to the contractor. Accordingly, the 15% advance payment has been divided into three parts and is paid to the contractor in stages as follows:

  • 5% of the total value of the contract to be released to the contractor upon the official site handover.
  • 5% of the total value of the contract upon approval of the construction time schedule by the project owner or by the appointed consulting office.
  • 5% of the total value of the contract upon completion of the temporary facilities at the jobsite (contractor's site office, warehouse, workshop, etc ).

Viable Solution: Because each instalment demands specific guarantees and missing any milestone suspends subsequent payments, a practical approach is to apply for the advance payment only after successfully completing all three stages.

Below is the link to the English translation of ACR 600-2024 (Google Drive):


Note: The available English translation is provisional and intended for informational purposes only; it may not completely reflect the source text with precision. A finalized version is currently being prepared for upload. Should you require an official, accurate translation of particular Articles, please contact me, and I will fulfill your request expeditiously.

Don't miss the next one. Click here to Get Tender and New Post Alerts Instantly!

https://buttondown.com/cihat

Laws, Decisions and Regulations in force

Laws, decisions and regulations in force governing the activities of international construction companies in Libya

Click the Google Drive link below to download any/all of the following PDF documents: Libyan Civil Code. Law No. 12/2004 on stamp tax. Law ...